Submitted to MHC - Trails and Greenways on July 18th, 2005

leaf Funding approved in the Capital Improvement Budget to renovate the equestrian facilities.Park.
leaf Maryland Department of Natural Resources has been notified and have visited the park to consider this project. The request is making its way through review and their support is expected as the statewide demand for equestrian facilities has increased.
leaf Estimates have been solicited for fencing and currently waiting on a response from a 3rd contractor.
leaf Public Works has been contacted to provide cost estimates on the surface material and it’s installation.
leaf We have received estimates on installing water stations.
leaf The renovations on the bathrooms to serve this facility have been completed.

 